Reports in P6

A
Anbin Ponnith 👤 Member for 17 years

Hai Shareef

S-Curve

If u Want to Create Manually S- Curve U try the Follwing steps

After Collapsing to Level 1,Click on Budget Cost

Ctrl+C

Open the Excel File & Paste It

Resource Histogram

If u Want to Have Separate Histogram for Each Resource u can Click on Resource Usage Profile Option

Click ->Display->Filter by Current project Resource

Now if u Click on the required resource u can see its profile

U Can use Same Print Option To Print

If U want to Know the Value of Corressponding Period u can use resource spreadsheet

Cummulative Budget Cost

U can Click on Activity Usage Spreedsheet-> Spreadsheet Field ->Select BudgetCost

After Collapsing to Level 1,Click on Budget Cost

Ctrl+C

Open the Excel File & Paste It

In that U Can See which activity Cost Is going beyound ur finish date

After That Check the Planned Start & Planned Finish Date for all the Resource Assigned to the activity





Regards

Anbin

S
Shareef Abdul Azeez 👤 Member for 20 years 9 months

Oops...



about the profile ...I found it!!!



We can use page setup from print preview and generate the profile...

Finally a relief!!

S
Shareef Abdul Azeez 👤 Member for 20 years 9 months

Thanx Anbin & Rodel for you response.!!



I used the activity spread sheet and generated the cumulative budgeted cost but I cant manage to copy the values from P6.Should I manually enter them in excel or is there some way to copy and paste from the spread sheet?



The next thing is my cumulatave budgeted cost keeps on extending beyond my project finish date . This is not a serious issue but I would like to know if this has got something to do with financial periods???



And about the assignment of budgeted cost ....I started off assigning the ’Remaining Units/Time’ to each resource and this calculates the ’Budgeted Units’ and thereby using the ’Price/Unit’ it calculates the ,Budgeted Cost’. Am I doing it right here???? Now the issue was with one activity where the resource assigned was of material type. Now for this for eg I have 8 No.s of bridge bearings each costing 10,000$; how can I enter cost. What I tried to do was to enter the Material Cost for this resource directly from the activity status form, coz other wise I would have to enter ’Budgeted Units’ as 8 which would multiply with the ’Price/Unit’ to give me the required amount. Is this the right way coz I confused that in this case the programme calculates ’Remaining Units/Time’ as Budgeted Units/duration (ie, 8/ Duration lets say 10 days ie, 8/10=0.8 which will normally be shown as 0 in the ’Remaining Units’ section.....Now this does not make sense which mean I will be using 0.8 of the bearing per day where as this is one whole item.................................In short how do we input material cost..!!!





Another difficuly I now face is that with P3 I used to generate resource projections and produce graphical reports for each resource instantly . It looks like I will have to manually move all the data to excel to do this.



How do you handle this???



Best Regards

Shareef

R
Rodel Marasigan 👤 Member for 19 years 7 months

Christopher,

Right Click at Activity Usage spreadsheet and select Spreadsheet Fields then under Time Interval->Cost groups double click Budgeted Labor Cost and under Unit groups double click Budgeted Labor Units then close. You should have both on the spreadsheet at you will see if cost or units are not distributed. If not make sure that the resource has a Price/unit define then select Tools-> Recalculate Assignment Cost.

J
James bid 👤 Member for 16 years 8 months

Hi Rodel!



I experienced confusion when I input the budgeted cost in resource tab making "cash" as the resource name, when I click the activity usage spreadsheet I found out that the budgeted cost was assigned only on the start of the activity whereas in default, it should be distributed evenly on the duration of the activity.

But when I tried to view the budgeted units , it works and distributed evenly.

What should I do?



Thanks

R
Rodel Marasigan 👤 Member for 19 years 7 months

Shareef,



Expenses export is referring to expenses tab in Activity Detail Window. If you define a resource you should use Resource Assignment as suggested by Anbin.

A
Anbin Ponnith 👤 Member for 17 years

Hai Shareef

If u Are Going to Type Budget Cost Directly

In the Resource Dictonary Please Check the Following Option

1.Select the Resource

1.Units & Price tab- >Price/unit->1.00 (it May be Zero)

2.Details->uncheck the calculate cost from unit

Recalulate Assignment Cost is Calculated base on Price/Unit*Budget Unit

3.Now if u run Recalculate Assignment Cost I hope it wont Change



Regards

Anbin

A
Anbin Ponnith 👤 Member for 17 years

Hi Shareef

As i Understood in P6 There is no Graphical Report as we Have in P3

U Can Try the Following Option

Click ->Activity Usage SpreadSheet

Collapse it to Level 1

Right Side u Can See Cost or Units Right Click on it ->click Spreedsheet Field

For Cummulative Cost

Cummulative->Cost->Cum Budget Total Cost or Cum Budget Material Cost

For The Period Cost

Time Interval ->Cost-> Budget Total Cost or Budget Material Cost

Right Click on The Time scale ->Select Date interval Week r Month

Just Copy The Budget total Cost & Cum Budget total cost value and paste it in Excel

Now u Can Manually Create S- Curve

Regards

Anbin

Forum Sponsor

Top Posters

Nick Johnson-Pond
3 posts
sairedz25
0 posts
Ahmed Awad
2 posts
Syed Shoeb
0 posts
Vimukthi
0 posts
bal aji
2 posts
Lee Mallek
23 posts
Viet Tran
9 posts
Ola Gbotoso
0 posts
Jaturapit Multongka
1 posts