S-Curve
If u Want to Create Manually S- Curve U try the Follwing steps
After Collapsing to Level 1,Click on Budget Cost
Ctrl+C
Open the Excel File & Paste It
Resource Histogram
If u Want to Have Separate Histogram for Each Resource u can Click on Resource Usage Profile Option
Click ->Display->Filter by Current project Resource
Now if u Click on the required resource u can see its profile
U Can use Same Print Option To Print
If U want to Know the Value of Corressponding Period u can use resource spreadsheet
Cummulative Budget Cost
U can Click on Activity Usage Spreedsheet-> Spreadsheet Field ->Select BudgetCost
After Collapsing to Level 1,Click on Budget Cost
Ctrl+C
Open the Excel File & Paste It
In that U Can See which activity Cost Is going beyound ur finish date
After That Check the Planned Start & Planned Finish Date for all the Resource Assigned to the activity
Regards
Anbin
Oops...
about the profile ...I found it!!!
We can use page setup from print preview and generate the profile...
Finally a relief!!
Thanx Anbin & Rodel for you response.!!
I used the activity spread sheet and generated the cumulative budgeted cost but I cant manage to copy the values from P6.Should I manually enter them in excel or is there some way to copy and paste from the spread sheet?
The next thing is my cumulatave budgeted cost keeps on extending beyond my project finish date . This is not a serious issue but I would like to know if this has got something to do with financial periods???
And about the assignment of budgeted cost ....I started off assigning the Remaining Units/Time to each resource and this calculates the Budgeted Units and thereby using the Price/Unit it calculates the ,Budgeted Cost. Am I doing it right here???? Now the issue was with one activity where the resource assigned was of material type. Now for this for eg I have 8 No.s of bridge bearings each costing 10,000$; how can I enter cost. What I tried to do was to enter the Material Cost for this resource directly from the activity status form, coz other wise I would have to enter Budgeted Units as 8 which would multiply with the Price/Unit to give me the required amount. Is this the right way coz I confused that in this case the programme calculates Remaining Units/Time as Budgeted Units/duration (ie, 8/ Duration lets say 10 days ie, 8/10=0.8 which will normally be shown as 0 in the Remaining Units section.....Now this does not make sense which mean I will be using 0.8 of the bearing per day where as this is one whole item.................................In short how do we input material cost..!!!
Another difficuly I now face is that with P3 I used to generate resource projections and produce graphical reports for each resource instantly . It looks like I will have to manually move all the data to excel to do this.
How do you handle this???
Best Regards
Shareef
Christopher,
Right Click at Activity Usage spreadsheet and select Spreadsheet Fields then under Time Interval->Cost groups double click Budgeted Labor Cost and under Unit groups double click Budgeted Labor Units then close. You should have both on the spreadsheet at you will see if cost or units are not distributed. If not make sure that the resource has a Price/unit define then select Tools-> Recalculate Assignment Cost.
Hi Rodel!
I experienced confusion when I input the budgeted cost in resource tab making "cash" as the resource name, when I click the activity usage spreadsheet I found out that the budgeted cost was assigned only on the start of the activity whereas in default, it should be distributed evenly on the duration of the activity.
But when I tried to view the budgeted units , it works and distributed evenly.
What should I do?
Thanks
Shareef,
Expenses export is referring to expenses tab in Activity Detail Window. If you define a resource you should use Resource Assignment as suggested by Anbin.
Hai Shareef
If u Are Going to Type Budget Cost Directly
In the Resource Dictonary Please Check the Following Option
1.Select the Resource
1.Units & Price tab- >Price/unit->1.00 (it May be Zero)
2.Details->uncheck the calculate cost from unit
Recalulate Assignment Cost is Calculated base on Price/Unit*Budget Unit
3.Now if u run Recalculate Assignment Cost I hope it wont Change
Regards
Anbin
Hi Shareef
As i Understood in P6 There is no Graphical Report as we Have in P3
U Can Try the Following Option
Click ->Activity Usage SpreadSheet
Collapse it to Level 1
Right Side u Can See Cost or Units Right Click on it ->click Spreedsheet Field
For Cummulative Cost
Cummulative->Cost->Cum Budget Total Cost or Cum Budget Material Cost
For The Period Cost
Time Interval ->Cost-> Budget Total Cost or Budget Material Cost
Right Click on The Time scale ->Select Date interval Week r Month
Just Copy The Budget total Cost & Cum Budget total cost value and paste it in Excel
Now u Can Manually Create S- Curve
Regards
Anbin