Show impact of planned vs actual resource
Forum Sponsor
Top Posters
Nick Johnson-Pond
3 posts
sairedz25
0 posts
Ahmed Awad
2 posts
Syed Shoeb
0 posts
Vimukthi
0 posts
bal aji
2 posts
Lee Mallek
23 posts
Viet Tran
9 posts
Ola Gbotoso
0 posts
Jaturapit Multongka
1 posts
Thanks
Paul
Paul,

That is easy. Create your baseline first using the 100hrs for 10 men. Use fixed/unit duration type so when adjusting time/unit it will automatically adjust the duration).
Then Maintain baseline and assigned as Project Baseline.
Adjust the schedule using 5men for 100hrs. See sample below: