Show impact of planned vs actual resource

R
Rodel Marasigan 👤 Member for 19 years 7 months

Paul,

That is easy. Create your baseline first using the 100hrs for 10 men. Use fixed/unit duration type so when adjusting time/unit it will automatically adjust the duration).

Then Maintain baseline and assigned as Project Baseline.

Adjust the schedule using 5men for 100hrs. See sample below:

Resource Impact