Manual update labour unit in resource usage spreadsheet
Forum Sponsor
Top Posters
Nick Johnson-Pond
3 posts
sairedz25
0 posts
Ahmed Awad
2 posts
Syed Shoeb
0 posts
Vimukthi
0 posts
bal aji
2 posts
Lee Mallek
23 posts
Viet Tran
9 posts
Ola Gbotoso
0 posts
Jaturapit Multongka
1 posts
Lucas,
Last check, are you using roles assignment as resource or resource itself? If roles make sure Edit Roles Assignment for Resource Planning also ticks.
Make sure that Remaining Early Units is display on the spreadsheet and not Remaining Early Cost.
It much easier if your profile is set to superadmin (less restriction)
I have checked and it is ticked.
Lucas,
You might not have privilege to that field. To set privilege select Admin-> Security Profiles. Tick Project then locates Edit Resource Assignment for Resource Planning and make sure it has tick.
Hi,
yes, it is present in the spreadsheet.
My duration setting is fixed duration and fixed unit. I check the help section and still cant solve it.
I can only make changes to the budgeted units, but not remaining unit and actual unit.
Kindly advice.
Regards
Lucas
Hi Lucas,
Is field remaining early units is present on the spreadsheet? What are your duration type settings? If fixed Units or Fixed Unit/Time then those setting are not updatable in spreadsheet but you can update them on the columns. Fixed Duration and Units or Fixed Duration and Unit/Time are only updatable settings on the spreadsheet.