Actual Quantity Compared to Baselne Quantity

D
D Artagnan 👤 Member for 17 years 8 months
R
Rodel Marasigan 👤 Member for 19 years 7 months

Don’t use the assignment module and used activity module instead. Click the activity usage spreadsheet icon or select View->Show on Bottom-> Activity Usage Spreadsheet. On the bottom right screen, right click and select spreadsheet fields. Under Cost or Units you can select BL?? and actual fields that you wanted to show. If running a report don’t use resource & roles assignment and used activity instead. Click the column and under cost and unit select BL?? and actual fields to use.

D
D Artagnan 👤 Member for 17 years 8 months

Thanks Rodel. However, there’s no option to choose the baseline actual/budgeted units in resource spreadesheet windows. I even tried reports but to no avail. Basically we want the periodic comparison of quantities againts baseline.

R
Rodel Marasigan 👤 Member for 19 years 7 months

You need to maintained and assigned the baseline first before you can select it. (It should be resource and cost loaded as per your actuals.) Or you can use current Project as a baseline.



If you want to show it on column select cost or unit then select BL? cost or unit. Or select Earned Value then select Plan & Actual (cost or unit)



If in activity usage spreadsheet, right click then select spreadsheet field then either cummulative or time interval select BL ??? (cost or unit) & Actual.

Forum Sponsor

Top Posters

Nick Johnson-Pond
3 posts
sairedz25
0 posts
Ahmed Awad
2 posts
Syed Shoeb
0 posts
Vimukthi
0 posts
bal aji
2 posts
Lee Mallek
23 posts
Viet Tran
9 posts
Ola Gbotoso
0 posts
Jaturapit Multongka
1 posts