P6 database is designed to hold up to 8 decimal points in some cases (cost_per_qty for instance is NUMERIC(21,8)) but the P6 interface allows you to see only 2 decimals.
Its because of the rounding up the figures. Proly, the data that you imported have more than 3 decimal places but P6 can only accomodate 2 decimal places. What P6 does is round it up accordingly.
Spider Project is most functional and powerful professional project management software.
The first SP version was launched in 1993 and since then it has been constantly improved. Today is used in 34 countries though most Spider Project customers are in Russia. Spider Project offers numerous unique functional features and is the only PM software that optimizes resource, cost, and material constrained schedules and budgets for projects and portfolios.
The unique features of Spider Project include Quantity Based Scheduling, Conditional Scheduling, Skill Scheduling, Optimal Resource, Cost and Material Leveling, Resource Critical Path Calculation, Cash and Material Flows Calculation and Management, Trend Analysis, Advanced Risk Simulation and Analysis, Calculation of Success Probability Trends, Calculation and Management of required Project Time and Cost Buffers, Application of Corporate Norms, Management of many Parallel Budgets, Multiple WBS and many others.
Spider Project was and is used for management of many large scale programs in Russia, including $51bln construction program for 2014 Winter Olympic Games preparation.
The application areas where Spider Project is successfully used include Aerospace, Banking, Construction, Defense, Energy, Engineering, Infrastructure, Manufacturing, Metallurgy, Mining, Oil & Gas, Railways, Retail, Shipbuilding, Software Development, Telecommunications, Utilities, etc.
P6-Auditor - Display information from Primavera P6 audit tables in a user-friendly format
Unifier-Archiver - Extract and archive important documents and attachments from Primavera Unifier
Unifier-Loader - Load data into and out of Unifier via Excel
PCM-Loader - Import data into Primavera Contract Management with flexible and secure, template-driven Excel spreadsheets
PCM-Archiver - Extract and archive important documents and attachments from Primavera Contract Management
PCM-Unifier Migrator - Automatically transfer live and historical data from Primavera Contract Management to Primavera Unifier with ease
Create Radically Better Construction Schedules with ALICE Technologies
Use the power of AI to create construction schedules that reduce risk while cutting costs and build time. With ALICE, develop the ideal schedule during preconstruction -- or recover projects that are off schedule and over budget.
Hai
Thanks all for ur reply.Actually I am getting Budget unit similar to BOQ.
My main Problem i am not able to get the Budget Cost in S Curve similar to Activity table
If i Run Recalculate Assignment Cost Total Budget Cost getting change
Once Again if i run Global Change i am able to get Correct Budget Cost in activity table any in my S Curve the Problem remain same
Is there any option to fix it
Regards
Anbin
P6 database is designed to hold up to 8 decimal points in some cases (cost_per_qty for instance is NUMERIC(21,8)) but the P6 interface allows you to see only 2 decimals.
Regards,
Andrew
Yeah i guess everybody confront the same problem. This happen too at Primavera 3. So what u need to do just play around the figure.
Anbin,
Its because of the rounding up the figures. Proly, the data that you imported have more than 3 decimal places but P6 can only accomodate 2 decimal places. What P6 does is round it up accordingly.
Hi Anbin
Sounds like a rounding up / down error.
Make sure that the two data sets are set to the same decimal places.
Best regards
Mike Testro