Export / Import routine P6

P
pat chadwick 👤 Member for 16 years 3 months

Hi Brad,



I’m trying to set up a weekly progress update routine for the activities.

These are the fields I am mapping to:



task_code status_code wbs_id task_name target_drtn_hr_cnt act_start_date act_end_date target_work_qty complete_pct act_work_qty user_number2 start_date end_date resource_list delete_record_flag



Activity ID Activity Status WBS Code Activity Name Original Duration(d) Actual Start Actual Finish (*)Budgeted Labor Units(d) Activity % Complete(%) (*)Actual Labor Units(d) Exp Mnhrs (*)Start (*)Finish (*)Resources Delete This Row