Export / Import routine P6
Forum Sponsor
Top Posters
Nick Johnson-Pond
3 posts
sairedz25
0 posts
Ahmed Awad
2 posts
Syed Shoeb
0 posts
Vimukthi
0 posts
bal aji
2 posts
Lee Mallek
23 posts
Viet Tran
9 posts
Ola Gbotoso
0 posts
Jaturapit Multongka
1 posts
Hi Brad,
Im trying to set up a weekly progress update routine for the activities.
These are the fields I am mapping to:
task_code status_code wbs_id task_name target_drtn_hr_cnt act_start_date act_end_date target_work_qty complete_pct act_work_qty user_number2 start_date end_date resource_list delete_record_flag
Activity ID Activity Status WBS Code Activity Name Original Duration(d) Actual Start Actual Finish (*)Budgeted Labor Units(d) Activity % Complete(%) (*)Actual Labor Units(d) Exp Mnhrs (*)Start (*)Finish (*)Resources Delete This Row