Hi Saurabh,
You mean the Nonlabor Units/Cost % Complete? Well, perhaps the reason is because, during the assignment of your resources the "Auto Compute Actuals" & "Calculate costs from units" is not tick.
You can perform this using global change.
Regards,
Arnold
See Arnold,
For Example if I update my non labor % complete in each activity, at the top summary bar I am not getting average of non labor % complete. How could I see them?
Regards,
Saurabh
Hi Kumar,
Try to allocate cost into your activities. Your programme must be cost loaded in order to roll up the % complete in the summary band.
Regards,
Arnold