P6 % complete

A
Arnold Puy 👤 Member for 19 years 1 month

Hi Saurabh,



You mean the Nonlabor Units/Cost % Complete? Well, perhaps the reason is because, during the assignment of your resources the "Auto Compute Actuals" & "Calculate costs from units" is not tick.



You can perform this using global change.



Regards,



Arnold

S
Saurabh Kumar 👤 Member for 16 years 6 months

See Arnold,



For Example if I update my non labor % complete in each activity, at the top summary bar I am not getting average of non labor % complete. How could I see them?



Regards,



Saurabh

A
Arnold Puy 👤 Member for 19 years 1 month

Hi Kumar,



Try to allocate cost into your activities. Your programme must be cost loaded in order to roll up the % complete in the summary band.



Regards,



Arnold

Forum Sponsor

Top Posters

Nick Johnson-Pond
3 posts
sairedz25
0 posts
Ahmed Awad
2 posts
Syed Shoeb
0 posts
Vimukthi
0 posts
bal aji
2 posts
Lee Mallek
23 posts
Viet Tran
9 posts
Ola Gbotoso
0 posts
Jaturapit Multongka
1 posts