Updating Level-of-Effort Activities

N
Neal Walsh 👤 Member for 18 years 9 months

And you’re in Forensic Claims? hmmmmmm......



Anyway, the LOE Activities act as a Hammock to the group it is spread across, and if you have assigned the LOE correctly (SS,FF) then your % complete will increase in relation to the Activities. You have to manually update your cost of work done allocated to these though.



Walshy

Forum Sponsor

Top Posters

Nick Johnson-Pond
3 posts
sairedz25
0 posts
Ahmed Awad
2 posts
Syed Shoeb
0 posts
Vimukthi
0 posts
bal aji
2 posts
Lee Mallek
23 posts
Viet Tran
9 posts
Ola Gbotoso
0 posts
Jaturapit Multongka
1 posts