Updating Level-of-Effort Activities
Forum Sponsor
Top Posters
Nick Johnson-Pond
3 posts
sairedz25
0 posts
Ahmed Awad
2 posts
Syed Shoeb
0 posts
Vimukthi
0 posts
bal aji
2 posts
Lee Mallek
23 posts
Viet Tran
9 posts
Ola Gbotoso
0 posts
Jaturapit Multongka
1 posts
And youre in Forensic Claims? hmmmmmm......
Anyway, the LOE Activities act as a Hammock to the group it is spread across, and if you have assigned the LOE correctly (SS,FF) then your % complete will increase in relation to the Activities. You have to manually update your cost of work done allocated to these though.
Walshy
set percent complete type to physical and change it