Customizing Timeline

M
Mark M 👤 Member for 18 years

Hi Ruel



Right click in the Gantt chart, select Timescale, under "Date Format", select "Show Ordinal Dates" & the necessary interval you require.

Note: If you select Ordinal Start as PS (Project Start) it will be based on your "Planned Start" date in the Projects screen, Dates tab.



Hope that helps.



Regards

Mark