Hi Ruel
Right click in the Gantt chart, select Timescale, under "Date Format", select "Show Ordinal Dates" & the necessary interval you require.
Note: If you select Ordinal Start as PS (Project Start) it will be based on your "Planned Start" date in the Projects screen, Dates tab.
Hope that helps.
Regards
Mark