Update Actual Dates from other Project(s)

M
Mah Fazel 👤 Member for 16 years 8 months
M
Mah Fazel 👤 Member for 16 years 8 months

Hi Arnold

Thanks for your attention and Reply.

But the problem is that when Import->Update Existing project, all of Activity parts imported (such as WBS,Pred. & Succ.) but we need to import only "Actual Dates"

(WBS’s are not same, some of links[pred. and succ.] of Sub-contractors are different from our Master Plan.)

Is there any way to Set only "Actual Dates" in master plan from Sub contractors updated plan.

Thanks again!

A
Arnold Puy 👤 Member for 19 years 1 month

Hi Mah,



Welcome to Planning Planet.



First of all, you need to create your Master Plan. In order to build the Master Plan as you’ve mentioned in your post by getting all the programmes from the Sub-Contractor and try to import all of these and in the "Import Action" select "Add Into Existing Project".



During updating, Open your Master Plan and import all the updated programmes of the Sub-Contractor. However, this time in the Import Action, select Update Existing Project".



Regards,



Arnold

Forum Sponsor

Top Posters

Nick Johnson-Pond
3 posts
sairedz25
0 posts
Ahmed Awad
2 posts
Syed Shoeb
0 posts
Vimukthi
0 posts
bal aji
2 posts
Lee Mallek
23 posts
Viet Tran
9 posts
Ola Gbotoso
0 posts
Jaturapit Multongka
1 posts