Total Original Duration!

A
Arnold Puy 👤 Member for 19 years 1 month

Hi Jonald,



First of all welcome to Planning Planet.



The Total Original Duration in Summary band calculated based on the "Default" calendar.



In order to change the summary duration you must select the calendar that your current project used. To do that, go to --> Enterprise --> Calendars, select the calendar that your project currently used and mark the check box "Default".



Regards,



Arnold

J
Jonald Calaycay 👤 Member for 17 years 9 months

Hi Izam,



The ES are all the same except the Gap is from 425 to 531.



Thank you for the reply.







Regards,





Jonald