Total Original Duration!
Forum Sponsor
Top Posters
Nick Johnson-Pond
3 posts
sairedz25
0 posts
Ahmed Awad
2 posts
Syed Shoeb
0 posts
Vimukthi
0 posts
bal aji
2 posts
Lee Mallek
23 posts
Viet Tran
9 posts
Ola Gbotoso
0 posts
Jaturapit Multongka
1 posts
Hi Jonald,
First of all welcome to Planning Planet.
The Total Original Duration in Summary band calculated based on the "Default" calendar.
In order to change the summary duration you must select the calendar that your current project used. To do that, go to --> Enterprise --> Calendars, select the calendar that your project currently used and mark the check box "Default".
Regards,
Arnold
Hi Izam,
The ES are all the same except the Gap is from 425 to 531.
Thank you for the reply.
Regards,
Jonald
How gap it is? Did ES equal each other