P3e - Budgeted against remaining early units?
Forum Sponsor
Top Posters
Nick Johnson-Pond
3 posts
sairedz25
0 posts
Ahmed Awad
2 posts
Syed Shoeb
0 posts
Vimukthi
0 posts
bal aji
2 posts
Lee Mallek
23 posts
Viet Tran
9 posts
Ola Gbotoso
0 posts
Jaturapit Multongka
1 posts
moved to p5 / p6 forum
Steve
Welcome to PP.
P3e is a different name for P6 and P5.
To your question:
I assume duration type is fixed duration & units.
For your ongiong activities the reported actual units were less than expected. So within the remaining duration youll have to do more work. Due to fixed duration, this has no influence on the remaining duration. All planned activities keep their position.
Result: Remaining units for the days which follow the data date (i.e. for the ongoing activities) are more than the planned units. Later they are equal again.
Regards
Dieter