P3e - Budgeted against remaining early units?

S
Steve Brown 👤 Member for 16 years 10 months
D
Dieter Wambach 👤 Member for 19 years 5 months

Steve



Welcome to PP.



P3e is a different name for P6 and P5.



To your question:

I assume duration type is fixed duration & units.

For your ongiong activities the reported actual units were less than expected. So within the remaining duration you’ll have to do more work. Due to fixed duration, this has no influence on the remaining duration. All planned activities keep their position.

Result: Remaining units for the days which follow the data date (i.e. for the ongoing activities) are more than the planned units. Later they are equal again.



Regards

Dieter