What am I missing here?
Forum Sponsor
Top Posters
Nick Johnson-Pond
3 posts
sairedz25
0 posts
Ahmed Awad
2 posts
Syed Shoeb
0 posts
Vimukthi
0 posts
bal aji
2 posts
Lee Mallek
23 posts
Viet Tran
9 posts
Ola Gbotoso
0 posts
Jaturapit Multongka
1 posts
All sorted now, thanks.
-I didnt have the "Allow users to specify the number of work hours for each time period box checked in the admin preferences.
Thanks for your input,
G
Hi Anoon, thanks for your reply
The activity calendar is 7 days/week, 8 hrs/day, no exceptions
The default calendar for the project is as above
The default global calendar for the EPS is 5 days/week, 8 hrs/day with some holidays included.
Even if the activity was using the default calendar instead of the assigned activity calendar, the finish dates in my original post still seem wrong
Cheers,
G
agree with anoon.
Gary,
check default calendar (global) and activity(s) calendars
cheers