What am I missing here?

G
Gary Whitehead 👤 Member for 17 years 2 months

All sorted now, thanks.



-I didn’t have the "Allow users to specify the number of work hours for each time period’ box checked in the admin preferences.



Thanks for your input,



G

G
Gary Whitehead 👤 Member for 17 years 2 months

Hi Anoon, thanks for your reply



The activity calendar is 7 days/week, 8 hrs/day, no exceptions



The default calendar for the project is as above



The default global calendar for the EPS is 5 days/week, 8 hrs/day with some holidays included.



Even if the activity was using the default calendar instead of the assigned activity calendar, the finish dates in my original post still seem wrong





Cheers,



G

A
Anoon Iimos 👤 Member for 19 years 8 months

Gary,



check default calendar (global) and activity(s) calendars



cheers

Forum Sponsor

Top Posters

Nick Johnson-Pond
3 posts
sairedz25
0 posts
Ahmed Awad
2 posts
Syed Shoeb
0 posts
Vimukthi
0 posts
bal aji
2 posts
Lee Mallek
23 posts
Viet Tran
9 posts
Ola Gbotoso
0 posts
Jaturapit Multongka
1 posts