How to spread manhour evenly

M
mike mark 👤 Member for 16 years 11 months
G
George Ridulme 👤 Member for 18 years

Hi Arnold,



My project has a future period bucket data, and i want to update my baseline since i just added a new activity, the problem is I cant update my baseline.



A message box appears indicating that "my project/baseline contains future period bucket data,cant run update baseline against it"



Thanks and Regards,



george

A
Arnold Puy 👤 Member for 19 years 1 month

Hi Mike,



Try to use the functionality of Future Period Bucket Planning. This is manually input depending on your forecast man-hour by daily, weekly or monthly.



You can also use the Assign Resource Curve to each activities. However, this will be more better and effective for only those activities takes a longer period.



Regards,



Arnold

A
Arnold Puy 👤 Member for 19 years 1 month

Hi George,



Which version of Primavera you are using? In P6 v7, even there is a future period bucket planning assigned to activities you can still update your baseline schedule.



There is a workaround, prior to updating restore first your baseline schedule and open it. Then, export it and import again and assign as baseline.



Regards,



Arnold

G
George Ridulme 👤 Member for 18 years

Thanks Arnold.



Im using P6, but am not sure what release this version is.



Anyway, thanks again for your help.





Regards,



George

A
Arnold Puy 👤 Member for 19 years 1 month

Hi George,



In order to know which version or release you are using, go to Help --> About Primavera, System Tab.



Regards,



Arnold

Forum Sponsor

Top Posters

Nick Johnson-Pond
3 posts
sairedz25
0 posts
Ahmed Awad
2 posts
Syed Shoeb
0 posts
Vimukthi
0 posts
bal aji
2 posts
Lee Mallek
23 posts
Viet Tran
9 posts
Ola Gbotoso
0 posts
Jaturapit Multongka
1 posts