Hi Arnold,
My project has a future period bucket data, and i want to update my baseline since i just added a new activity, the problem is I cant update my baseline.
A message box appears indicating that "my project/baseline contains future period bucket data,cant run update baseline against it"
Thanks and Regards,
george
Hi Mike,
Try to use the functionality of Future Period Bucket Planning. This is manually input depending on your forecast man-hour by daily, weekly or monthly.
You can also use the Assign Resource Curve to each activities. However, this will be more better and effective for only those activities takes a longer period.
Regards,
Arnold
Hi George,
Which version of Primavera you are using? In P6 v7, even there is a future period bucket planning assigned to activities you can still update your baseline schedule.
There is a workaround, prior to updating restore first your baseline schedule and open it. Then, export it and import again and assign as baseline.
Regards,
Arnold
Thanks Arnold.
Im using P6, but am not sure what release this version is.
Anyway, thanks again for your help.
Regards,
George
Hi George,
In order to know which version or release you are using, go to Help --> About Primavera, System Tab.
Regards,
Arnold