Also, after assigning baseline, check dates in START and FINISH columns rather than early dates.
hi
Thank you very much for your help
regards
prem
Hi Prem,
P6 is correct in this situation. To differntiate between these dates, ADD these columns "Early Start", "Early Finish", "Start", "Finish", "Planned Start" and "Planned Finish".
Early Date columns will give you the dates, based on the completed activities or in progress activities.
Start & Finish Columns and Planned Dates will match, as you have not assigned any baseline.
Now, when you will update the program and will assign the baseline, please make sure that baseline uses "Budgeted Values with Current Dates".
This option you can find in Admin Preferences --> Earned Value Tab --> Earned Value Calculation
Cheers,
Ravi