issue with the baseline

P
prem kumar, 👤 Member for 21 years 3 months
A
A D 👤 Member for 19 years 1 month

Also, after assigning baseline, check dates in START and FINISH columns rather than early dates.


A
A D 👤 Member for 19 years 1 month

Hi Prem,



P6 is correct in this situation. To differntiate between these dates, ADD these columns "Early Start", "Early Finish", "Start", "Finish", "Planned Start" and "Planned Finish".



Early Date columns will give you the dates, based on the completed activities or in progress activities.



Start & Finish Columns and Planned Dates will match, as you have not assigned any baseline.



Now, when you will update the program and will assign the baseline, please make sure that baseline uses "Budgeted Values with Current Dates".



This option you can find in Admin Preferences --> Earned Value Tab --> Earned Value Calculation



Cheers,



Ravi

Forum Sponsor

Top Posters

Nick Johnson-Pond
3 posts
sairedz25
0 posts
Ahmed Awad
2 posts
Syed Shoeb
0 posts
Vimukthi
0 posts
bal aji
2 posts
Lee Mallek
23 posts
Viet Tran
9 posts
Ola Gbotoso
0 posts
Jaturapit Multongka
1 posts