Resource Assignments

D
Duy Huynh 👤 Member for 18 years 1 month

Hi,



I think you must use a small trick in P6, create resources 2&4 with Maximum Unit/time = 0 and assign following your excel sequence.



Use the Units&Price in Resource pool to adjust those values to fit your monthly assignment.



For example, resource 2 has price/unit of $10, max unit/time of 8h/day but he doesn’t work on any activity in January- 09, Set data as follow:

Effective date --- max unit/time ---price/unit

1-Jan-08 --- 8h/d --- $10/h

1-Jan-09 --- 0h/d --- $10/h

1-Feb-09 --- 8h/d --- $10/h



If the same resource assigned to another activities the same January-09 then this method useless.



Cheers,

Duy







Cheers,

Duy

G
Gary Whitehead 👤 Member for 17 years 2 months

Hi Clay,



I moved your post to the P6 forum as I think you’ll get better responses here.



I’m not aware of a way to insert blank resources into P6 reports, but if it’s always the same resources which are omitted, you should be able to write a fairly simple macro to do that for you once the data is in excel.



Cheers,



Gary

Forum Sponsor

Top Posters

Nick Johnson-Pond
3 posts
sairedz25
0 posts
Ahmed Awad
2 posts
Syed Shoeb
0 posts
Vimukthi
0 posts
bal aji
2 posts
Lee Mallek
23 posts
Viet Tran
9 posts
Ola Gbotoso
0 posts
Jaturapit Multongka
1 posts