Hi,
I think you must use a small trick in P6, create resources 2&4 with Maximum Unit/time = 0 and assign following your excel sequence.
Use the Units&Price in Resource pool to adjust those values to fit your monthly assignment.
For example, resource 2 has price/unit of $10, max unit/time of 8h/day but he doesn’t work on any activity in January- 09, Set data as follow:
Effective date --- max unit/time ---price/unit
1-Jan-08 --- 8h/d --- $10/h
1-Jan-09 --- 0h/d --- $10/h
1-Feb-09 --- 8h/d --- $10/h
If the same resource assigned to another activities the same January-09 then this method useless.
Cheers,
Duy
Cheers,
Duy
Hi Clay,
I moved your post to the P6 forum as I think youll get better responses here.
Im not aware of a way to insert blank resources into P6 reports, but if its always the same resources which are omitted, you should be able to write a fairly simple macro to do that for you once the data is in excel.
Cheers,
Gary