Milestone dates are changing

S
Shahzad Ahmad 👤 Member for 18 years 4 months

Hi Yusuke



Could you please explain in detail.

you are working on Base line Schedule or Milestones project start date are changing while updated sch.





Base line shecdule you can fix MS by relation.



Check your Project Caleander start date etc.



shahzad

D
Dieter Wambach 👤 Member for 19 years 5 months

Yusuke



I don’t really understand your question. Milestones - exept project start - depend on other activities. If there is a delay, the milestone will be shifted accordingly.

Maybe that’s the reason: You have activities which were planned to start before the data date. Those will be shifted to the data date because there can’t be any (scheduled) start earlier than data date - and your milestones accordingly. All dates earlier than data date must have the status "actual".



Constraints should be avoided and restricted to contractual dates - for my opinion.



Just a guess. Was this related to your problem?



Regards

Dieter

Forum Sponsor

Top Posters

Nick Johnson-Pond
3 posts
sairedz25
0 posts
Ahmed Awad
2 posts
Syed Shoeb
0 posts
Vimukthi
0 posts
bal aji
2 posts
Lee Mallek
23 posts
Viet Tran
9 posts
Ola Gbotoso
0 posts
Jaturapit Multongka
1 posts