Hi Yusuke
Could you please explain in detail.
you are working on Base line Schedule or Milestones project start date are changing while updated sch.
Base line shecdule you can fix MS by relation.
Check your Project Caleander start date etc.
shahzad
Yusuke
I don’t really understand your question. Milestones - exept project start - depend on other activities. If there is a delay, the milestone will be shifted accordingly.
Maybe that’s the reason: You have activities which were planned to start before the data date. Those will be shifted to the data date because there can’t be any (scheduled) start earlier than data date - and your milestones accordingly. All dates earlier than data date must have the status "actual".
Constraints should be avoided and restricted to contractual dates - for my opinion.
Just a guess. Was this related to your problem?
Regards
Dieter