Durations VS Schedule

A
António Faria 👤 Member for 17 years 5 months

In the "mouche"! :)



Thanks a lot. It worked. No luck was needed ;)



I check other open projects and I notice the following:



the 4 projects that I import to Primavera were without this option selected. New ones, Primavera has this option as default.



One more time, thanks.

AF

D
Dieter Wambach 👤 Member for 19 years 5 months

António

There is a project parameter "Link Budget and At Completion for not started activities":

View Project --> select your project (must be open) --> Tab "Calculations" --> mark "Link..."

Good luck!

Dieter