In the "mouche"! :)
Thanks a lot. It worked. No luck was needed ;)
I check other open projects and I notice the following:
the 4 projects that I import to Primavera were without this option selected. New ones, Primavera has this option as default.
One more time, thanks.
AF
António
There is a project parameter "Link Budget and At Completion for not started activities":
View Project --> select your project (must be open) --> Tab "Calculations" --> mark "Link..."
Good luck!
Dieter