P6 - Can i link the resource to durations of activity

D
DAVID SMITH 👤 Member for 22 years 2 months
A
Ali Farhat 👤 Member for 17 years 7 months

David, if you use the "Fixed Units/time" P6 will change duration NOT the budgeted units if the units/time changed. Oliver’s way work

D
DAVID SMITH 👤 Member for 22 years 2 months

I will have a fiddle, I kind of want it the other way around, as in, if the budgetted resource changes then the duration moves up and down with it.



Will have a play and see what I can find.



Many thanks Oliver



Dave

O
Oliver Melling 👤 Member for 19 years 1 month

Dave,



Experiment with the duration type.



If you use ’Fixed Units/Time’ then there is a link between the duration and the labour units.



i.e. if the duration changes the planned labour units change.

Forum Sponsor

Top Posters

Nick Johnson-Pond
3 posts
sairedz25
0 posts
Ahmed Awad
2 posts
Syed Shoeb
0 posts
Vimukthi
0 posts
bal aji
2 posts
Lee Mallek
23 posts
Viet Tran
9 posts
Ola Gbotoso
0 posts
Jaturapit Multongka
1 posts