Vimukthi
0 posts
bal aji
2 posts
Lee Mallek
23 posts
Viet Tran
9 posts
Ola Gbotoso
0 posts
Jaturapit Multongka
1 posts
David, if you use the "Fixed Units/time" P6 will change duration NOT the budgeted units if the units/time changed. Olivers way work
I will have a fiddle, I kind of want it the other way around, as in, if the budgetted resource changes then the duration moves up and down with it.
Will have a play and see what I can find.
Many thanks Oliver
Dave
Dave,
Experiment with the duration type.
If you use Fixed Units/Time then there is a link between the duration and the labour units.
i.e. if the duration changes the planned labour units change.