Problem during imporing to P5 from P3

A
arun kumar 👤 Member for 18 years 2 months
A
Arnold Puy 👤 Member for 19 years 1 month

Hi Arun,



Try to check your Planning Unit in P3. P6 does not support Week & Month for Planning Unit. It is always in Days & Hours.



First try to convert your planning unit in P3 to days prior to import to P6.



hth.





Arnold