Problem during imporing to P5 from P3
Forum Sponsor
Top Posters
Nick Johnson-Pond
3 posts
sairedz25
0 posts
Ahmed Awad
2 posts
Syed Shoeb
0 posts
Vimukthi
0 posts
bal aji
2 posts
Lee Mallek
23 posts
Viet Tran
9 posts
Ola Gbotoso
0 posts
Jaturapit Multongka
1 posts
Hi Arun,
Try to check your Planning Unit in P3. P6 does not support Week & Month for Planning Unit. It is always in Days & Hours.
First try to convert your planning unit in P3 to days prior to import to P6.
hth.
Arnold