The sooner the better
Forum Sponsor
Top Posters
Nick Johnson-Pond
3 posts
sairedz25
0 posts
Ahmed Awad
2 posts
Syed Shoeb
0 posts
Vimukthi
0 posts
bal aji
2 posts
Lee Mallek
23 posts
Viet Tran
9 posts
Ola Gbotoso
0 posts
Jaturapit Multongka
1 posts
Hello Hannes,
Create a predessesor milestone with fs relationship to the task and put a start on constraint on it, it will turn red if the data date will pass the constraint date
regards Alphons
I have an activity with a lot of float - for technical reasons - but it is good to start this activity as soon as possible, to be earlier than compatitors
Be more specific please
regards Alphons