Hello Hannes,

Create a predessesor milestone with fs relationship to the task and put a start on constraint on it, it will turn red if the data date will pass the constraint date



regards Alphons

H
Hannes de Bruyne 👤 Member for 20 years 10 months

I have an activity with a lot of float - for technical reasons - but it is good to start this activity as soon as possible, to be earlier than compatitors