Scheduling without actual units
Forum Sponsor
Top Posters
Nick Johnson-Pond
3 posts
sairedz25
0 posts
Ahmed Awad
2 posts
Syed Shoeb
0 posts
Vimukthi
0 posts
bal aji
2 posts
Lee Mallek
23 posts
Viet Tran
9 posts
Ola Gbotoso
0 posts
Jaturapit Multongka
1 posts
Hi,
If you want that your Actual Units will remain zero during progress, you must have to go to Project, select your current project. In Project Detail Tab select Calculations and uncheck “Recalculate Actual Units and Cost when duration % complete changes”.
Activity Type = Task Dependent and Duration Type must be equal to “Fixed Duration & Units”. However, if your Duration Type = Fixed Duration and Units/Time, during progress the Actual Units = 0 and “At Completion Units” is equal to “Remaining Units” and is not equal to “Budgeted Units”.
Arnold
I think the most of problem is when we fixed the durations and unit/times,the autual units will go with the %comp