Scheduling without actual units

B
Beck Lee 👤 Member for 18 years
A
Arnold Puy 👤 Member for 19 years 1 month

Hi,



If you want that your Actual Units will remain zero during progress, you must have to go to Project, select your current project. In Project Detail Tab select Calculations and uncheck “Recalculate Actual Units and Cost when duration % complete changes”.



Activity Type = Task Dependent and Duration Type must be equal to “Fixed Duration & Units”. However, if your Duration Type = Fixed Duration and Units/Time, during progress the Actual Units = 0 and “At Completion Units” is equal to “Remaining Units” and is not equal to “Budgeted Units”.



Arnold

Q
Qiu Wei 👤 Member for 17 years 11 months

I think the most of problem is when we fixed the durations and unit/times,the autual units will go with the %comp

Forum Sponsor

Top Posters

Nick Johnson-Pond
3 posts
sairedz25
0 posts
Ahmed Awad
2 posts
Syed Shoeb
0 posts
Vimukthi
0 posts
bal aji
2 posts
Lee Mallek
23 posts
Viet Tran
9 posts
Ola Gbotoso
0 posts
Jaturapit Multongka
1 posts