P5: Progress Spotlight’s labor units

Y
Yusuke Kamui 👤 Member for 18 years

Hi Mark,

Thanks for your quick reply. I did what you instructed and it filter out all those activites as what the progress spotlight indicated. But the problem is, in the column "budgeted labor units", it still shows the labor units for whole duration of the project not the specific labor units of that activity in that filtered period or time frame set by the filter.



Any idea?





Thanks.


M
Mark M 👤 Member for 18 years

Hi Yusuke



Just using the "progress spotlight" I don’t believe this is possible, however, if you set up a filter equivalent to the spotlight and display the budgeted labor units column you will see the total budgeted units for those activities.



ie, If your progress spotlight is looking forward a month your filter would be:

"{all of the following}

Where activity status is not equal to completed

and {any of the following}

Where activity status equals in progress

or early start is less than or equals DD+1M"



This should give you the desired outcome. Hope this helps.



Cheers

Mark

Forum Sponsor

Top Posters

Nick Johnson-Pond
3 posts
sairedz25
0 posts
Ahmed Awad
2 posts
Syed Shoeb
0 posts
Vimukthi
0 posts
bal aji
2 posts
Lee Mallek
23 posts
Viet Tran
9 posts
Ola Gbotoso
0 posts
Jaturapit Multongka
1 posts