P5: Progress Spotlight’s labor units
Forum Sponsor
Top Posters
Nick Johnson-Pond
3 posts
sairedz25
0 posts
Ahmed Awad
2 posts
Syed Shoeb
0 posts
Vimukthi
0 posts
bal aji
2 posts
Lee Mallek
23 posts
Viet Tran
9 posts
Ola Gbotoso
0 posts
Jaturapit Multongka
1 posts
Hi Mark,
Thanks for your quick reply. I did what you instructed and it filter out all those activites as what the progress spotlight indicated. But the problem is, in the column "budgeted labor units", it still shows the labor units for whole duration of the project not the specific labor units of that activity in that filtered period or time frame set by the filter.
Any idea?
Thanks.
Hi Yusuke
Just using the "progress spotlight" I dont believe this is possible, however, if you set up a filter equivalent to the spotlight and display the budgeted labor units column you will see the total budgeted units for those activities.
ie, If your progress spotlight is looking forward a month your filter would be:
"{all of the following}
Where activity status is not equal to completed
and {any of the following}
Where activity status equals in progress
or early start is less than or equals DD+1M"
This should give you the desired outcome. Hope this helps.
Cheers
Mark