I have tried to copy and paste avtivities for changing activity ID's to a new sequence with respect to activity dates. But unfortunately the Sequence of activities did not change...
For example;
Before After the process
A1020 AD2020
A1030 AD2030
A1070 AD2070
A1050 AD2050
Why this is happening like this? Means, why A1070 renumber to AD2070 instead of the seaquencial, AD2050??
There is a "seat-of-the-pants" method if your feeling brave.
Make a copy of your programme - Just in case!
Set "Auto Numbering Defaults to...
Prefix "Z" (or any you wish)
Suffix "10000" (or any you wish)
Increment "10" (or any you wish)
Now select all tasks you want renumbering (all if thats the case) and copy task, paste task selecting all paste options including "only between copied tasks" for logic.
You should now have a programme twice as big as before; twins in fact in all but tasks ID. Filter out the old tasks by ID and delete them. Bish Bash Bosh, what is left is the original programme but renumbered.
Only takes a few mins so have a go and see if you get what you expect.
The only downside is that any external logic links will be broken.
I have just taken over a plan which has been developed but not baselined yet.
The activity IDs are all over the place and I would like to re-number them from the say 100000 and going down in 10s (100010, 100020 and so on) can this be done without upsetting all the logic?
If the xxxxxxx part of your activity ID is the same length then you will be easily able to execute a global change; Similar to this;
Where Activity ID starts with EB
Then Activity ID = MW + Right String,Activity ID, n
Where n = the number of characters counting from the right of the activity ID to the first character after the original EB
eg. EBxxxxxx (n=5) changes to MWxxxxx.
Have a couple of trys witin an inert project to get it staright in your mind what you need to do, but it is entirely possible. I make sure that I set my IDs up in a manner where I can conduct this change as required, because Ive come across some PMs that like their activity IDs to be related to someone or something.
Spider Project is most functional and powerful professional project management software.
The first SP version was launched in 1993 and since then it has been constantly improved. Today is used in 34 countries though most Spider Project customers are in Russia. Spider Project offers numerous unique functional features and is the only PM software that optimizes resource, cost, and material constrained schedules and budgets for projects and portfolios.
The unique features of Spider Project include Quantity Based Scheduling, Conditional Scheduling, Skill Scheduling, Optimal Resource, Cost and Material Leveling, Resource Critical Path Calculation, Cash and Material Flows Calculation and Management, Trend Analysis, Advanced Risk Simulation and Analysis, Calculation of Success Probability Trends, Calculation and Management of required Project Time and Cost Buffers, Application of Corporate Norms, Management of many Parallel Budgets, Multiple WBS and many others.
Spider Project was and is used for management of many large scale programs in Russia, including $51bln construction program for 2014 Winter Olympic Games preparation.
The application areas where Spider Project is successfully used include Aerospace, Banking, Construction, Defense, Energy, Engineering, Infrastructure, Manufacturing, Metallurgy, Mining, Oil & Gas, Railways, Retail, Shipbuilding, Software Development, Telecommunications, Utilities, etc.
P6-Auditor - Display information from Primavera P6 audit tables in a user-friendly format
Unifier-Archiver - Extract and archive important documents and attachments from Primavera Unifier
Unifier-Loader - Load data into and out of Unifier via Excel
PCM-Loader - Import data into Primavera Contract Management with flexible and secure, template-driven Excel spreadsheets
PCM-Archiver - Extract and archive important documents and attachments from Primavera Contract Management
PCM-Unifier Migrator - Automatically transfer live and historical data from Primavera Contract Management to Primavera Unifier with ease
Create Radically Better Construction Schedules with ALICE Technologies
Use the power of AI to create construction schedules that reduce risk while cutting costs and build time. With ALICE, develop the ideal schedule during preconstruction -- or recover projects that are off schedule and over budget.
If you can't edit your activity IDs then you probably don't have sufficient rights. Speak to your administrator or login with an admin password.
If you can't edit your activity IDs then you probably don't have sufficient rights. Speak to your administrator or login with an admin password.
I have tried to copy and paste avtivities for changing activity ID's to a new sequence with respect to activity dates. But unfortunately the Sequence of activities did not change...
For example;
Before After the process
A1020 AD2020
A1030 AD2030
A1070 AD2070
A1050 AD2050
Why this is happening like this? Means, why A1070 renumber to AD2070 instead of the seaquencial, AD2050??
Any help?? I am using P6 v6.2
Glen,
There is a "seat-of-the-pants" method if your feeling brave.
Make a copy of your programme - Just in case!
Set "Auto Numbering Defaults to...
Prefix "Z" (or any you wish)
Suffix "10000" (or any you wish)
Increment "10" (or any you wish)
Now select all tasks you want renumbering (all if thats the case) and copy task, paste task selecting all paste options including "only between copied tasks" for logic.
You should now have a programme twice as big as before; twins in fact in all but tasks ID. Filter out the old tasks by ID and delete them. Bish Bash Bosh, what is left is the original programme but renumbered.
Only takes a few mins so have a go and see if you get what you expect.
The only downside is that any external logic links will be broken.
Activity ID is no longer as important now. you can certainly export to excel, mod the ID and import it back
HTH
Alex
Hi all,
just going off on a tangent slightly.
I have just taken over a plan which has been developed but not baselined yet.
The activity IDs are all over the place and I would like to re-number them from the say 100000 and going down in 10s (100010, 100020 and so on) can this be done without upsetting all the logic?
Thanks in advance.
GED
Go to Edit, Replace and select ID column. Enter change xxx to yyy
Jineesh,
If the xxxxxxx part of your activity ID is the same length then you will be easily able to execute a global change; Similar to this;
Where Activity ID starts with EB
Then Activity ID = MW + Right String,Activity ID, n
Where n = the number of characters counting from the right of the activity ID to the first character after the original EB
eg. EBxxxxxx (n=5) changes to MWxxxxx.
Have a couple of trys witin an inert project to get it staright in your mind what you need to do, but it is entirely possible. I make sure that I set my IDs up in a manner where I can conduct this change as required, because Ive come across some PMs that like their activity IDs to be related to someone or something.
Andy
Jineesh
Try the Global Change (Tools --> Global Change --> click on the "Help" button. There is good information, so you should be able to use it.
If then youll have any questions, dont hesitate to ask again.
Regards
Dieter