Autocalculate actuals units with Phisical % comp.
Forum Sponsor
Top Posters
Nick Johnson-Pond
3 posts
sairedz25
0 posts
Ahmed Awad
2 posts
Syed Shoeb
0 posts
Vimukthi
0 posts
bal aji
2 posts
Lee Mallek
23 posts
Viet Tran
9 posts
Ola Gbotoso
0 posts
Jaturapit Multongka
1 posts
theres a workaround to roll-up physical % complete, consult your PAR
You need to run summerized project in order to see the summary %
HTH
Alex
You can not roll up Physical % complete as they may all be calculated on a different basis.
Paul E Harris
Eastwood Harris Pty Ltd, Melbourne, Australia
Planning and Scheduling Training Manual & Book Publishers, Consulting and Training
www.eh.com.au
Hi Paul,
What Im expecting is to see the "physical % complete" to be calculated up to the project summary. Right now, if I enter 5% physical complete on a task, the overall project physical % complete is still showing 0% even though I have some tasks underneath having physical % complete. How come??? How to have the overall projects physical complete status?
In the Activities Workspace, Activities details, General tab.
Paul E Harris
Eastwood Harris Pty Ltd, Melbourne, Australia
Planning and Scheduling Training Manual & Book Publishers, Consulting and Training
www.eh.com.au
Hi Paul, thanks for idea...but how can you do it?....
"The Physical % Complete field may be linked to the Activity % Field by setting the activities % Complete type equal to Physical."
Have a nice day.
Mirko.
Hi Paul,
How can you do it?....
"The Physical % Complete field may be linked to the Activity % Field by setting the activities % Complete type equal to Physical."
Where to set it?
The Units % Complete will update your Actuals Units and a change to actual units will update the Units % Complete.
If you make the activities’ % Complete type equal to Units then this will link the Units% Complete to Activity % Complete and this value will be displayed on the bars.
The Physical % Complete field may be linked to the Activity % Field by setting the activities % Complete type equal to Physical.
Paul E Harris
Eastwood Harris Pty Ltd, Melbourne, Australia
Planning and Scheduling Training Manual & Book Publishers, Consulting and Training
www.eh.com.au
Hi Mirko
One of the options is to use - > Project Option - Calculation
"Update Actual Unit when duration % complete changes"
This will automatical change the actual unit when you changes your "Duration % Complete" - But not the Phical % Complete.
Before you run this option you can run a global change to align the duration % Complete with Physical % Complete.
But because you updated the duration % Complete it will affect some of the activity type on the remaining duration
Need to test run it before you can use this process.
HTH
Alex