Autocalculate actuals units with Phisical % comp.

M
mirko piras 👤 Member for 18 years 3 months
A
Anoon Iimos 👤 Member for 19 years 8 months

there’s a workaround to roll-up physical % complete, consult your PAR

A
Alex Wong 👤 Member for 23 years 4 months

You need to run summerized project in order to see the summary %



HTH



Alex

P
Paul Harris 👤 Member for 25 years 2 months

You can not roll up Physical % complete as they may all be calculated on a different basis.



Paul E Harris

Eastwood Harris Pty Ltd, Melbourne, Australia

Planning and Scheduling Training Manual & Book Publishers, Consulting and Training

www.eh.com.au

Y
Yusuke Kamui 👤 Member for 18 years

Hi Paul,

What I’m expecting is to see the "physical % complete" to be calculated up to the project summary. Right now, if I enter 5% physical complete on a task, the overall project physical % complete is still showing 0% even though I have some tasks underneath having physical % complete. How come??? How to have the overall project’s physical complete status?

P
Paul Harris 👤 Member for 25 years 2 months

In the Activities Workspace, Activities details, General tab.



Paul E Harris

Eastwood Harris Pty Ltd, Melbourne, Australia

Planning and Scheduling Training Manual & Book Publishers, Consulting and Training

www.eh.com.au

M
mirko piras 👤 Member for 18 years 3 months

Hi Paul, thanks for idea...but how can you do it?....

"The Physical % Complete field may be linked to the Activity % Field by setting the activities % Complete type equal to Physical."



Have a nice day.



Mirko.

Y
Yusuke Kamui 👤 Member for 18 years

Hi Paul,

How can you do it?....

"The Physical % Complete field may be linked to the Activity % Field by setting the activities % Complete type equal to Physical."



Where to set it?

P
Paul Harris 👤 Member for 25 years 2 months

The Units % Complete will update your Actuals Units and a change to actual units will update the Units % Complete.



If you make the activities’ % Complete type equal to Units then this will link the Units% Complete to Activity % Complete and this value will be displayed on the bars.



The Physical % Complete field may be linked to the Activity % Field by setting the activities % Complete type equal to Physical.



Paul E Harris

Eastwood Harris Pty Ltd, Melbourne, Australia

Planning and Scheduling Training Manual & Book Publishers, Consulting and Training

www.eh.com.au

A
Alex Wong 👤 Member for 23 years 4 months

Hi Mirko



One of the options is to use - > Project Option - Calculation

"Update Actual Unit when duration % complete changes"



This will automatical change the actual unit when you changes your "Duration % Complete" - But not the Phical % Complete.



Before you run this option you can run a global change to align the duration % Complete with Physical % Complete.



But because you updated the duration % Complete it will affect some of the activity type on the remaining duration



Need to test run it before you can use this process.



HTH



Alex

Forum Sponsor

Top Posters

Nick Johnson-Pond
3 posts
sairedz25
0 posts
Ahmed Awad
2 posts
Syed Shoeb
0 posts
Vimukthi
0 posts
bal aji
2 posts
Lee Mallek
23 posts
Viet Tran
9 posts
Ola Gbotoso
0 posts
Jaturapit Multongka
1 posts