Schedule % and Performance % Summery
Forum Sponsor
Top Posters
Nick Johnson-Pond
3 posts
sairedz25
0 posts
Ahmed Awad
2 posts
Syed Shoeb
0 posts
Vimukthi
0 posts
bal aji
2 posts
Lee Mallek
23 posts
Viet Tran
9 posts
Ola Gbotoso
0 posts
Jaturapit Multongka
1 posts
Mohammed,
At least you fixed it.
Ill track the guy down at work next week if I remember and ask him what our problem was again, I thought it was the same but that didnt sound like the same fix.
Andy
Wallla,
I found it, I got the solution,
I must assign resources with unit price even 1$, that is when the summery for S PCT% & P PCT% will be calculated.
Regards
Mohamed
Dear Andrew,
I do not know, but it dose not work. Stil facing the same problem. Ive repeated the whole project,yet with no use.
Thank you for interacting.
Mohamed
Mohammed,
Came across this one the other week, and a bloke I know came up with the soloution.
In a nutshell the fault existed for us when we deleted an activity out of the project which existed in the baseline.
So you will need to carry out a new baseline and the missing data will be returned.
Im sure thats how it went, Ill check tomorrow.
Andy