Schedule % and Performance % Summery

A
Andrew Dick 👤 Member for 19 years 4 months

Mohammed,

At least you fixed it.



I’ll track the guy down at work next week if I remember and ask him what our problem was again, I thought it was the same but that didn’t sound like the same fix.



Andy

M
Mohammed Abo El Magd 👤 Member for 21 years 6 months

Wallla,

I found it, I got the solution,

I must assign resources with unit price even 1$, that is when the summery for S PCT% & P PCT% will be calculated.



Regards

Mohamed

M
Mohammed Abo El Magd 👤 Member for 21 years 6 months

Dear Andrew,

I do not know, but it dose not work. Stil facing the same problem. I’ve repeated the whole project,yet with no use.



Thank you for interacting.

Mohamed

A
Andrew Dick 👤 Member for 19 years 4 months

Mohammed,

Came across this one the other week, and a bloke I know came up with the soloution.



In a nutshell the fault existed for us when we deleted an activity out of the project which existed in the baseline.



So you will need to carry out a new baseline and the missing data will be returned.



I’m sure that’s how it went, I’ll check tomorrow.



Andy

Forum Sponsor

Top Posters

Nick Johnson-Pond
3 posts
sairedz25
0 posts
Ahmed Awad
2 posts
Syed Shoeb
0 posts
Vimukthi
0 posts
bal aji
2 posts
Lee Mallek
23 posts
Viet Tran
9 posts
Ola Gbotoso
0 posts
Jaturapit Multongka
1 posts