Original Duration equal to total NOT by level

D
Diane Armstrong 👤 Member for 18 years 2 months

Ok... I think we solved this one... I filtered all Hammock items and it corrected itself.



Don’t know what Hammock activities are but thats for another lesson ;)



Thanks Diane

D
Diane Armstrong 👤 Member for 18 years 2 months

Hi Dieter... this didn’t change my results except give me a total at the bottom of each level vs. the top.



I may not be explaining this clearly.



Eg. The total project has 463 hours at level 1. But Level 4 also show 463 at each of its jobs although the job doesn’t total 463... it should only show a total of 6.



Hope this explains it better.



Also... i know this is Suretrak but it I don’t see a category for Suretrak and P3 should be fairly simular



Thanks for your assistance

Diane

D
Dieter Wambach 👤 Member for 19 years 5 months

Hi Diane

Move your mouse into the table area --> right click (or "Format") --> organize --> right side within the window column "Total" --> select top or bottom --> select "Organize now".

This works in P3 and should work in Suretrak as well.

Regards

Dieterr

Forum Sponsor

Top Posters

Nick Johnson-Pond
3 posts
sairedz25
0 posts
Ahmed Awad
2 posts
Syed Shoeb
0 posts
Vimukthi
0 posts
bal aji
2 posts
Lee Mallek
23 posts
Viet Tran
9 posts
Ola Gbotoso
0 posts
Jaturapit Multongka
1 posts