P5 Variance in Summary level ---Original Duration
Forum Sponsor
Top Posters
Nick Johnson-Pond
3 posts
sairedz25
0 posts
Ahmed Awad
2 posts
Syed Shoeb
0 posts
Vimukthi
0 posts
bal aji
2 posts
Lee Mallek
23 posts
Viet Tran
9 posts
Ola Gbotoso
0 posts
Jaturapit Multongka
1 posts
Thanks Guys,
I understood that this is a unsolved problem where we are using more than one calender in a project,Otherwise we need to switch in to WBS summary level.
Thanks for quick response & cooperation.
Regards,
Jiso
Jiso,
If you follow this thread and study the other 2 that it references then you will see some of the frustrations we come across with this subject.
Primavera Duration Threads
Andy
Hi Jiso
As activities in Primavera can have different calendars, durations show in the summary bars by default are assigned to the default calendar.
If youll study PP youll find quite a few threads on this topic.
Regards
Dieter