P5 Variance in Summary level ---Original Duration

J
Jiso Thomas 👤 Member for 18 years 3 months
J
Jiso Thomas 👤 Member for 18 years 3 months

Thanks Guys,



I understood that this is a unsolved problem where we are using more than one calender in a project,Otherwise we need to switch in to WBS summary level.



Thanks for quick response & cooperation.



Regards,



Jiso




D
Dieter Wambach 👤 Member for 19 years 5 months

Hi Jiso

As activities in Primavera can have different calendars, durations show in the summary bars by default are assigned to the default calendar.

If you’ll study PP you’ll find quite a few threads on this topic.

Regards

Dieter